UNDERGROUND INFRASTRUCTURE INSTALLATIONS
Busselton Water main Installation
Water main installation and connection under a capital works expansion program for Busselton Water Board.
Project Overview
Leeuwin Civil was engaged to install an approximately 1.62 Km, 375 mm PVC Class 12 pipe as part of a capital works expansion program to increase water main capacity for the Busselton. This involved carrying out all infill works along existing road reserves owned by the City of Busselton under City requirements. All verge works on private residential verges also had to be restored to pre-existing states.
Scope of Works:
- Service location and protection
- Trenching, backfilling, and pipe installation
- Reinstatement works (including crossings, road reserves, footpaths, and kerbing)
- Residential driveway reinstatement works
- Revegetation works.
Project Details
CLIENTBusselton Water Board
LOCATIONBusselton West Australia
STATUSComplete